Sogeti USA
     
 

Sogeti's E-Business Suite User manual

 
  Back  
 
 
 
     
 

3.8.2 Edit & Create Agreements:

 
     
 

By default, Oracle will create an agreement for each Project using the Project number. This agreement is created using a default amount of $100,000. This amount has no significance unless the terms of this agreement are changed.

 
     
 

Navigation:
Projects> Billing> Agreements

 
     
 
  • Navigate to the Agreements Screen
  • Query the old agreement using the agreement# (same as project number, unless it has been changed by the user)
 
     
 
 
     
 
  • Change the agreement number to the client PO #. Agreement number must be unique for a customer. If the same number already exists, the system will not let you create another agreement with the same number. Hint: Append the version number (.1, .2, etc. to the PO #).
  • Change the amount to the actual PO amount.
  • If the PO has a hard limit and invoicing beyond this limit will not be accepted by the client, check the "Invoice Hard Limit" box.
  • Do NOT check the "Revenue Hard Limit" box.
  • If there are multiple purchase orders for this project, clear the screen and create all purchase orders. This time, you are creating an agreement. Hence, you will be required to enter additional things like Customer Name, Agreement Type, Terms, etc.
  • Save the Purchase Orders
 
     
     
 
 
  Back  
 
© 2005 Sogeti USA LLC - Proprietary and Confidential.
 
This document is best viewed in Microsoft Internet Explorer 6.0+ in 1024x768